Engineers from the Ulaanbaatar City Investment Agency conducted an on-site inspection of the flood protection embankment, pedestrian walkway, and landscaping project being implemented along the Selbe River as part of the Agency’s client-side supervision responsibilities.
Under the project, construction of the flood protection embankment has been fully completed. Landscaping and green space development works are currently in progress. The contractor, Silla Group LLC, stated that the remaining works are being carried out according to schedule and are expected to be completed and handed over by the 10th of next month.
The Agency’s engineers will continue to carry out client-side supervision to ensure that the project is delivered in accordance with quality standards, technical specifications, and the approved schedule, enabling the development to be completed and commissioned on time.